electrical-substationsClient: Abu Dhabi Transmission and Despatch Company (Transco)
Consultant: Lahmeyer International
Main EPC Contractor: Emirates Technical Associates
Construction time: 11 months.
Built-up area: 7,800m2.
Description: The first underground substation for high voltage power of 132KV/11 KV built in a unique building is located opposite the Presidential Palace, Abu Dhabi. On a plot size of 70m x 70m, the substation has a basement floor on -3 level (2,340m2), technical floors on -2 and -1 level. The bottom floor is 14.5m below ground level.